| |
| Current Projects |
|
|
|
|
|
|
Korba West Power Company Limited, 1X600 MW KWPCL Avanta Raigarh Project, Near Bade Bhandar Village, Raigarh District. Chattisgarh. |
Erection, Testing & Assistance for commissioning, Trial Operation and Handing over of Turbine and Generator Set and its Auxiliaries, HP/LP Heater and Painting, etc., of 1 X 600 MW |
06.12.2011 |
69,400,000 |
Under Mobilization |
|
Visa Power Limited Unit 1 of 2X600 MW VPL, Deveri & Dumarpali, Raigarh District. Chattisgarh. |
Erection, Testing, & Commissioning, Trial Operation and Handing over of Boiler and its Auxiliaries including ESP, Air Preheaters, Ducts and Dampers, Fans, Fuel Piping, Boiler Integral Piping, Power cycle piping, Chemical dozing system, Lining & Insulation, Final painting, etc of Unit 1 of 2 X 600 MW |
22.07.2011 |
617,365,000 |
5% Completed |
|
Dainik Bhaskar Power Limited Unit 1 of 2x600 MW DBPL, Janjgir, Champa District. Chattisgarh. |
Erection, Testing, & Commissioning, Trial Operation and Handing over of Boiler and its Auxiliaries including ESP, Air Preheaters, Ducts and Dampers, Fans, Fuel Piping, Boiler Integral Piping, Power cycle piping, Chemical dozing system, Lining & Insulation, Final painting, etc of Unit 1 of 2 X 600 MW |
18.02.2011 |
571,297,500 |
18% Completed |
|
NTECL Vallur Thermal Power Project Kuruvimedu Village Poneeri Taluk, Tamilnadu . |
Erection, Testing, Commissiong & handing over of complete Power Cycle piping supplied under SG&TG packages, accessories, associated equpmts/systems, final painting for Unit 1&2 of 2 x 500 MW |
15.07.2010 |
216,864,000 |
55% Completed |
|
Maharashtra State Power Generation CoLtd Chandrapur Super Thermal PowerStation Expn Project(2X500 MW),Chandrapur Maharashtra . |
Material handling & unloading, Erection, Testing and Commissioning of complete Boiler structures,Pressure parts,ESP,Fans,Power cycle piping,coal mills&feeders insulation & final painting of Unit 9,2x500 MW |
23.01.2010 |
489,440,923 |
20% Completed |
|
NTECL Vallur Thermal Power Project Kuruvimedu Village Poneeri Taluk, Tamilnadu . |
Erection, Testing, and commissioning of complete Boiler Structures, pressure parts, Non-Pressure parts , Rotaing Machines including supply and Application of Final Painting for Unit # 2 of 2x500 MW set |
20.05.2009 |
313,974,140 |
80% Completed |
|
Gujarat State Energy Generation Ltd., Near Hazira,Village Mora, Dist. Surat , Gujarat . |
Erection, Testing, Commissioning,Final Painting and Handing over of 1 x 292 TPH HRSG and its auxiliaries, Steel Stack, Piping etc, for 1x350 MW combined Power Plant at GSEG, Hazira ,Dist. Surat, Gujarat |
18.03.2009 |
82,034,029 |
95% completed |
|
|
|
|